Pakistan’s Rs 1,600 billion refinery plan could nearly double petrol output
Pakistan’s oil regulator projects that upgrades at five refineries could lift high-speed diesel output by about 47 percent and save roughly $1 billion a year in foreign exchange by cutting fuel imports.

Pakistan plans to invest an estimated $5.7 billion, or about Rs 1,600 billion, in upgrades at five major oil refineries. The Oil and Gas Regulatory Authority (OGRA) projects that the work could nearly double domestic petrol production and raise high-speed diesel output by about 47 percent.
Under OGRA’s projections, refineries could produce 21,251 tonnes of petrol a day, up from 10,702 tonnes. Daily high-speed diesel production could rise from 21,237 tonnes to 31,288 tonnes. It could not be independently confirmed when or where OGRA issued the projections.
The projects are due for completion between 2028 and 2030. Alongside the increase in output, each of the five refineries aims to bring both its petrol and its diesel up to Euro-V standards once the work is complete.
Pakistan Refinery Limited (PRL) has the largest estimated investment of the five, at $1.7 billion, and the earliest scheduled finish, in 2028. PARCO’s upgrade is estimated at $1.4 billion and is one of three projects targeting completion in 2029.
National Refinery Limited (NRL) and Attock Refinery are also aiming to finish in 2029, with estimated costs of $1 billion and $600 million, respectively. Cnergyico’s upgrade is expected to cost $1 billion and is scheduled for completion in 2030, the latest of the five target dates.
The investment is intended to strengthen Pakistan’s refining capacity so the country can meet more of its fuel needs from domestic production. By reducing reliance on imported petroleum products, the upgrades could save about $1 billion in foreign exchange each year and improve the country’s foreign exchange position.